A view of our new
bathrooms
We had a very productive week. The brewery is looking much less like an archaeological dig. As expected, the in-ground portion of the plumbing rough-in was finished this week. The plumber has been doing an awesome job so far.

On Thursday, our concrete guys came back to fill and compact the dirt and on Friday, they poured the floor. Over the coming week we will be getting ready to put the walk-in cooler back together. You can click on the picture to the right to see a slideshow of the progress so far.